UK Renovation Process and Fees

Taking on a renovation and home redesign is a big project with many parts and people involved. If this is your first time doing so in the UK, you may find the following useful.

1. Buying the Property

Parties involved

  • Solicitor / conveyancer

  • Surveyor

Timeline

  • 8–16 weeks

2. Initial Planning + Design Feasibility

Parties involved

  • Interior Designer

  • Architect

  • Structural Engineer

Timeline

  • 4–8 weeks

3. Concept & Layout Design

Parties involved

  • Interior Designer

  • Architect

Timeline

  • 4–8 weeks

4. Planning Permission + Regulatory Approvals

Parties involved

  • Architect

  • Planning Consultant (optional)

  • Party Wall Surveyor

  • Local Authority Planning Officers

Timeline

  • Planning approval: 8–10 weeks

  • Party wall notice periods + award: 1–3 months

5. Technical + Construction Drawings

Parties involved

  • Architect

  • Interior Designer

  • Structural Engineer

  • M&E Consultant (optional)

Timeline

  • 8–16 weeks

6. Building Control Approval

Parties involved

  • Local Authority Building Control or Approved Inspector

Timeline

  • 2–8 weeks for initial approval

  • inspections ongoing throughout project

7. Tender + Contractor Selection

Parties involved

  • Main Contractor

  • Quantity Surveyor

  • Architect/Interior Designer/Project Manager

Timeline

  • 3–6 weeks

8. Construction Phase

Parties involved

  • Main Contractor

  • Subcontractors

  • Building Control Inspector

  • Interior Designer / Project Manager

Typical costs (very dependent on scale + finish)

  • £1,500–£3,000 per m² for full refurbishment

  • Extensions and basements cost more

Typical timelines

  • Light renovation: 8–12 weeks

  • Medium renovation: 4–8 months

  • Full refurb + extension: 8–18 months

9. Completion + Handover

Parties involved

  • Main Contractor

  • Building Control Inspector

Timeline

  • 2–6 weeks